Haryana Vidyut Prasaran Nigam Ltd. have awarded the following contract to Mohan Energy Corporation Pvt. Ltd. for power transmission lines
220 KV SINGLE
CIRCUIT TRANSMISSION
LINE BETWEEN
NILOKHERI AND KARNAL
- Length : 20
Km
- Contract
completion : 15
months
- Scope :
total turnkey
construction of
transmission
line
- Number of
locations : 66
- Type of
tower : 4 type
with all
extension upto
18m
- Conductor :
ACSR Zebra
length 61 Km
- Earth Wire :
7/3.15mm G.S.
Earth wire -
20km
Line was handed over to HVPNL on 23rd April 2008.
220 KV DOUBLE CIRCUIT TRANSMISSION LINE BETWEEN YTPP (YAMUNANAGAR THERMAL POWER PROJECT) ANDÂ NILOKHERI
- Length : 52
Km
- Contract
completion : 15
months
- Scope :
total turnkey
construction of
transmission
line
- Number of
locations : 174
- Type of
tower : 4 type
with all
extension upto
25m
- Conductor :
ACSR Zebra
length 315 Km
- Earth Wire :
7/3.15mm G.S.
Earth wire -
53km
Line is under progress and will be completed by July 2010
220 KV DOUBLE CIRCUIT TRANSMISSION LINE BETWEEN YTPP (YAMUNANAGAR THERMAL POWER PROJECT) ANDÂ ABDULLAPUR
- Length : 29
Km
- Contract
completion : 15
months
- Scope :
total turnkey
construction of
transmission
line
- Number of
locations : 93
- Type of
tower : 4 type
with all
extension upto
25m
- Conductor :
ACSR Zebra
length 172 Km
- Earth Wire :
7/3.15mm G.S.
Earth wire -
29km
Line was handed over to HVPNL in March 2009.
66 KV SINGLE
CIRCUIT TRANSMISSION
LINE BETWEEN LOHARA
AND BABAIN
- Length : 9
Km
- Contract
completion : 12
months
- Scope :
total turnkey
construction of
transmission
line
- Number of
locations : 4
- Type of
tower : 2 type
- Conductor :
ACSR Panther
length 28 Km
- Earth Wire :
7/2.50mm G.S.
Earth wire - 9km
Line was handed over to HVPNL in November 2009.
|